Photo: Tony Webster from Minneapolis, Minnesota, United States / Wikimedia Commons, CC BY-SA 2.0
Construction of the New Lock at the Soo in Sault Ste. Marie has passed the halfway mark, the U.S. Army Corps of Engineers Detroit District announced, keeping the $3.2 billion project on schedule to finish in 2030.
Phase 3, the main construction contract awarded July 1, 2022, to Kokosing Alberici Traylor LLC of Westerville, Ohio, is now 50% complete, according to the Corps announcement as reported by Design and Construction Report. The contractor had completed about $975 million of work through the end of August.
The project matters far beyond the Upper Peninsula. About 88% of U.S. domestic iron ore shipping relies on the Poe Lock, which opened in 1969, and there is no other lock at the Soo large enough for the biggest lake freighters. A breakdown there would ripple through steel mills and the auto supply chain.
What is being built
The new chamber will be the second Poe-sized lock at the complex, built on the site of the old Sabin and Davis locks. Phase 3 includes cofferdams at both ends, demolition of the Sabin Lock and filling of the Davis Lock, bedrock excavation, lock walls and floor, miter gates and the lock’s mechanical and electrical systems. It also adds a hands-free mooring system, rehabilitates downstream approach walls and builds a new pump well.
Steel parts, including miter gates, ship arrestors and culvert valves, are being fabricated off site while crews pour mass concrete for the walls and floor.
By the numbers
The lock will need about 400,000 cubic yards of concrete. As of August, 140,198 cubic yards had been placed. More than 600 people are working on the project, the Corps said.
“The progress made here is a direct reflection of the more than 600 people working on this project,” said Mick Awbrey, chief of the Corps’ Integrated Project Office, in the announcement.
Awbrey put the volume in everyday terms. “If you were to build an average sidewalk that you see in a neighborhood, with 400,000 cubic yards of concrete, you could build a sidewalk from Sault Ste. Marie, Michigan, to Orlando, Florida,” he said. The concrete placed through August would stretch nearly to Dayton, Ohio, by the same measure, the Corps said.
The Corps calls the new lock one of its highest-priority commercial navigation projects and has used it as an example of faster project delivery under its civil works program.
Why Michigan has a stake
Iron ore from Minnesota and the U.P. moves through the Soo to steel mills on the lower lakes, and the locks are also a tourism draw for Sault Ste. Marie, where the Corps runs a visitor center and viewing platform during the shipping season. The Detroit District oversees about 3,150 miles of shoreline and 81 harbors and channels in Michigan and parts of Indiana, Wisconsin and Minnesota.
The Soo Locks close to commercial traffic each winter for maintenance, and the Corps posts construction updates on its Detroit District website. For more on Great Lakes shipping, see our report on the Gordie Howe bridge’s first three months, and find more from the north in Northern Michigan & U.P..